Critical Lift Plan
Load and capacity calculation, crane configuration and ground conditions.
HOT PASS
QA/QC Document Control hotpassqc.com
Project
Job No.
Client
Sheet ____ of ____
Description of the Lift and the Load
Over 75% of chart capacityTandem / multi-craneBlind liftOver live process or equipmentOver or near personnelPersonnel platformNear power linesNon-standard riggingOver waterHigh value / long lead itemOther
Crane / Equipment Data
YesNo — state below
YesNo
YesNo
Load calculation — everything the hook carries
Weight (lb)
A
Load weight (from drawing, nameplate or weigh ticket — state source)
Jib / auxiliary head (stowed or erected, per chart)
E
Wire rope, and any other chart deduction
F
Total gross load (A + B + C + D + E)
G
Chart capacity at the worst radius and this configuration
H
Percent of capacity (F ÷ G × 100) — enter as %
Work the calculation at the largest radius the load will reach, not the pick radius, and use the chart for the exact configuration erected. Attach the chart page used.
YesN/A
YesNo
YesNo
HP-CL-01 | Rev 0 | Side 1 of 2Free blank form from HOT PASS QA/QC — hotpassqc.com
Critical Lift Plan
Rigging schedule, conditions, personnel and the pre-lift check.
HOT PASS
QA/QC Document Control hotpassqc.com
Project
Job No.
Client
Lift No.
#
Rigging Item
Size / Type
Rated Capacity
Sling Angle
D/d Ratio
1
2
3
4
5
6
Sling capacity falls with the angle — a two-leg sling at 30° from horizontal carries half what it does vertically. Rate every leg at the angle it will actually work at.
YesNo
YesNo
YesNo
Overhead Power Lines
YesNoN/A
Role
Name (print)
Company
Qualification / Cert No.
Lift Director
Crane Operator
Qualified Rigger
Signal Person
Spotter
Competent Person
#
Pre-lift check — immediately before the pick
Yes
No
N/A
1
Pre-lift meeting held with everyone involved; plan walked through
2
Signals agreed, and radio channel confirmed clear
3
Crane set level, on firm ground, outriggers and pads as planned
4
Swing and travel path clear; nobody under the load or in the swing radius
5
Load free, unbolted and not restrained; no unexpected attachments
6
Trial lift performed — load raised clear and held, rigging checked
7
Landing area prepared, cribbing set and able to take the load
8
Stop-work authority stated to the crew, and the stop signal agreed
Lift director / Date
Crane operator / Date
Site superintendent / Competent person / Date
HP-CL-01 | Rev 0 | Side 2 of 2Free blank form from HOT PASS QA/QC — hotpassqc.com