HOTPASS ← Back to Hot Pass
Free Resources

Blank QA/QC forms you can print today.

The forms every welding and pipeline contractor ends up rebuilding in Excel — WPS, welder qualification, nonconformance, RFI, weld map, punch list, pressure test and an 11×17 isometric sheet, the safety permits that stop a job when they are missing — hot work, confined space, critical lift — plus material and pipe references. No signup, no watermark, no expiry. Print them, copy them, put your own logo on them — they're yours.

These are the same record structures Hot Pass uses, so if you ever move off paper, nothing has to be re-thought.

Welding Procedure Specification

HP-WPS-01 · Rev 0 · 2 sides

Joints, base metals, filler metals, positions, preheat, PWHT, gas, electrical and technique, plus a pass-by-pass parameter table and a joint sketch area.

Open the form →Portrait

Welder Qualification & Continuity

HP-WPQ-01 · Rev 0 · 2 sides

Test coupon, ranges qualified and test results on the front — and a continuity log on the back, because a lapsed qualification is what most often fails a package after the welding is done.

Open the form →Portrait

Nonconformance Report

HP-NCR-01 · Rev 0

Type, severity, description, root cause, corrective action, and disposition — through to closure with three signature lines.

Open the form →Portrait

Request for Information

HP-RFI-01 · Rev 0

Question against the drawings, spec, or scope, with document reference, schedule impact, and a response block for the answer.

Open the form →Portrait

Weld Map / Weld Log

HP-WM-01 · Rev 0

19 rows: weld ID, joint, station, welder, WPS, heat number, size, date welded, X-ray, bends, and status.

Open the form →Landscape

Punch List

HP-PL-01 · Rev 0

19 rows for a walkdown, tracked from identification through completion and client sign-off.

Open the form →Landscape

Pipe Data & Flange Bolting

HP-PIPE-01 · Rev 0 · Landscape

OD, wall, ID, weight per foot and gallons of water per foot for Sch 10 / 40 / 80, plus flange bolt counts, diameters and wrench sizes.

Open the reference →Landscape

Material Specs & Grades

HP-MAT-01 · Rev 0 · 2 sides

The specs most common in pipeline and facility work — pipe, fittings, flanges, bolting — and crucially which ones go together. Plus what to check on an incoming MTR.

Open the reference →Portrait

Isometric Sheet

HP-ISO-01 · Rev 0 · 11×17

Tabloid sketch sheet with an isometric grid for drawing a pipe run by hand, plus line number, spec, test pressure, NDE, drawing number and approval. Grid can be switched off.

Open the form →11×17 Landscape

Pressure Test Record

HP-PT-01 · Rev 0

Hydrostatic or pneumatic: system details, test pressures, a ten-row reading log, and witness signatures.

Open the form →Portrait

Job Safety Analysis

HP-JSA-01 · Rev 0

For the pre-job briefing: permits and PPE, eight step / hazard / control rows, emergency and muster details, and a crew sign-on so the attendance list is on the same sheet as the analysis.

Open the form →Portrait

Hot Work Permit

HP-HW-01 · Rev 0

Welding, cutting and grinding outside a designated area: a fourteen-point precaution check, a gas test log with the limits printed on the sheet, fire watch and post-work monitoring — and a closure block, because the permit that never gets cancelled is the one that gets found open in an audit.

Open the form →Portrait

Critical Lift Plan

HP-CL-01 · Rev 0 · 2 sides

The calculation an auditor actually looks for: gross load built up line by line, chart capacity at the worst radius, and percent of capacity as its own number. Plus crane configuration, ground bearing, rigging schedule with sling angles, personnel qualifications and a pre-lift check.

Open the form →Portrait

Confined Space Entry Permit

HP-CS-01 · Rev 0 · 2 sides

Hazards, isolation verified at the point of isolation, and an eight-row atmospheric log with the acceptable limits and the test order on the page. Entrants sign in and out so the attendant can count who is inside, and the permit does not close until every line has a time out.

Open the form →Portrait

Bell Hole Report

HP-BH-01 · Rev 0 · 2 sides

For the dig itself: what the in-line inspection predicted written down beside what was actually found, because a verification dig that only records the second one verifies nothing. Excavation and as-found pipe data, coating and CP readings taken before the coating is disturbed, an eight by nine wall thickness grid, remaining strength, disposition and backfill.

Open the form →Portrait

Welding Parameter Record

HP-WP-01 · Rev 0

The WPS says what was qualified. This says what was actually set at the machine: amps, volts, travel speed and heat input logged pass by pass, root through cap, with preheat and interpass measured beside the values the procedure requires. The heat input formula is printed on the sheet, and there is one box for the question an inspector is really asking — was every parameter inside the range.

Open the form →Portrait

SWPPP Inspection Report

HP-SWI-01 · Rev 0

The one filled in standing on the site: why the inspection was triggered, rainfall for the event, the condition of each control, what left the site, and a certification statement — which most stormwater permits require before the report counts.

Open the form →Portrait

BMP Installation & Maintenance Log

HP-BMP-01 · Rev 0

Fourteen rows for every erosion and sediment control installed, maintained or removed — with quantity, who did it and who verified it.

Open the form →Landscape

Dust Control & Air Quality Log

HP-AIR-01 · Rev 0

Watering, covered loads and surface stabilisation by date, area and haul road, with water used and conditions at the time.

Open the form →Landscape

Waste & Hazardous Materials Log

HP-WST-01 · Rev 0

What left the site, who hauled it, under what manifest and where it went — plus a spill and release record on the same sheet.

Open the form →Landscape

Printing these properly

These forms are the easy part.

The hard part is what happens after they're filled in — the weld log that doesn't match the isometric, the NCR nobody closed, the MTR that was never filed, and the three weeks at the end of the job spent assembling a turnover package out of folders and memory.

That's what Hot Pass is for. Same records, but expiries, open NCRs and missing paperwork surface while you can still fix them, and the job book compiles itself.

See how it works →

Or read what actually goes in a turnover package — all thirteen sections, and the cross-checks that get one rejected.

HOT PASS QA/QC — DOCUMENT CONTROL SYSTEM Plans FAQs Contact Refund Policy